Substrate & Surface Guide

Substrate & Surface Preparation Guide

Flawless Microcement Starts Below the Surface

Ready-to-use microcement (MyCROCEMENT™) adheres to almost any rigid substrate, but the key to a long-lasting, crack-free finish lies in proper surface preparation. Because MyCROCEMENT™ is a micro-topping system applied at a total thickness of ~2mm, the final finish is only as stable as the surface beneath it.

Before opening a bucket, use this guide to assess, clean, repair, and prime your specific surface.

Quick Reference Surface Matrix

Substrate TypeCompatibilityKey Risk factorCore Prep RequirementRecommended PrimerFiberglass Mesh Needed?
Ceramic / Porcelain TileCompatibleGhosting / Grout lines showingDeep clean, fill grout joints flushMyPRIMEROptional over grout
Drywall, Plaster & BlueboardIdealUneven suction / Joint movementTape seams, mud flat, sand smoothMyPRIMEROver board seams only if needed
Cement Backer BoardIdealJoint movementScrew tight to framing; tape seams with alkali-resistant meshMyPRIMERRequired over board seams
Concrete & Cement ScreedsIdealCracks & rising moistureGrind surface, fill structural cracksMyPRIMEROver crack repairs if needed
Plywood, MDF & OSBConditionalStructural flex & moisture expansionFasten securely, seal edges, stabilizeMyPRIMEROptional in case of any uncertainty
Waterproofing Membranes (Wedi, Kerdi, Hydro Ban)IdealUncured membrane / Seam flex
Laminate & CountertopsCompatibleSlick, non-porous finishAbrade with 80-grit, degreaseMyPRIMEROptional (High-impact/High-stress zones)
Metal & GlassConditionalAdhesion / Non-porous flexHeavy mechanical scuffing, specialty degreaseMyPRIMERCase-by-case evaluation
Unstable or Rotted WoodNot RecommendedStructural failureMust be completely removed and replaced prior to applicationN/AN/A

Detailed Preparation Guidelines

1. Drywall, Plaster, Plasterboard & Cement Board

Drywall and cement backer board provide ideal, uniform surfaces when properly jointed and stabilized.

  • Inspect & Stabilize: Ensure all panels are screw-fastened tightly to framing with zero bounce. Screw heads must be fully countersunk.
  • Seam Prep: Tape seams and corners with alkali-resistant mesh tape and mud as usual to achieve a Level 4 or Level 5 finish. Sand completely smooth.
  • Clean: Ensure the surface is dry and completely free of dust, painter’s tape, silicone, or caulk residue.
  • Prime: Apply a uniform coat of MyPRIMER to equalize porosity and create protection between the board face and joint mud. Allow to dry completely (1–2 hours).
  • Mesh: Embed fiberglass mesh in MyBASE over board seams to eliminate stress lines.

2. Existing Tile, Porcelain & Masonry

Existing tile is one of the most common microcement substrates, but telegraphing (grout lines showing through the finished coat) must be strictly prevented.

  • Inspect: Tap tiles to identify hollow or loose spots. Remove loose tiles and fill voids flush with high-strength repair mortar.
  • Clean & Degrease: Scrub thoroughly with TSP (Trisodium Phosphate) or an industrial degreaser to remove soap scum, oils, and waxes. Rinse clean.
  • De-gloss: Heavy-sand glazed tiles using 80-grit sandpaper to break the sheen and create a mechanical profile for bonding. Vacuum away all sanding dust.
  • Fill Joints & Level: Fill grout lines flush with a non-shrinking joint filler or MyBASE.
  • Prime: Apply 1–2 coats of MyPRIMER to establish a solid mechanical key.
  • Reinforce: For ultimate ghosting prevention on tile grids, embed alkali-resistant fiberglass mesh into your first coat of MyBASE, troweling and sanding smooth.

3. Concrete Slabs & Cementitious Screeds

Concrete provides an ultra-rigid base, but moisture movement and existing cracks require careful preparation.

  • Cure Time: Concrete must be fully cured (minimum 28 days for new pours).
  • Moisture Testing: Subfloor moisture content must be below 4% (Relative Humidity < 75%, or MVER < 3 lbs / 1,000 sq ft / 24 hrs).
  • Abrasion: Mechanical grinding or etching is required to remove laitance, old sealers, paint, or curing compounds, achieving a concrete surface profile of CSP 1–2.
  • Crack Repair: V-cut any hairline or structural cracks, fill with epoxy gel or rigid repair mortar, and cross-stitch with carbon fiber staples if active movement is suspected.
  • Prime: Apply MyPRIMER to seal porous screeds or power-troweled concrete.

4. Waterproofing Membranes (Showers & Wet Areas)

Sheet membranes (e.g., Schluter-KERDI, Wedi) and liquid membranes (e.g., Laticrete Hydro Ban, RedGard) make excellent backings when handled correctly.

  • Cure Check: Ensure the membrane system is installed strictly to manufacturer specs and fully cured.
  • Clean: Wipe clean of jobsite dust, oils, or thinset residue.
  • Prime: Apply MyPRIMER evenly across the surface.
  • Mesh Reinforcement: Embed alkali-resistant fiberglass mesh into MyBASE across all corners, transitions, niches, and change-of-plane seams. Full-coverage mesh is strongly recommended in direct water-contact zones.

5. Wood Substrates (Plywood, MDF, OSB)

Wood expands, contracts, and flexes with ambient humidity. Overcoming this movement requires strict mechanical locking and full-coverage reinforcement.

  • Rigidity: Subfloors and countertops must be a minimum of 3/4” thick, tongue-and-groove, screw-fastened every 6 inches along joists/framing with zero flex under footprint or heavy load.
  • Seam Sealing: Fill seams between sheets with polyurethane sealant or epoxy filler to prevent edge swelling.
  • Moisture Barrier: Seal all exposed bare edges and undersides of wood panels to prevent ambient moisture absorption and warping.
  • Full Mesh Reinforcement (Mandatory): Because wood moves dynamically, you must embed an alkali-resistant fiberglass mesh into MyBASE across the entire wooden surface to bridge expansion movements across joints.
  • Prime: Apply MyPRIMER thoroughly before base coating.

6. Countertops, Laminate & Formica

Transforming existing laminate or solid surface countertops requires breaking the factory sheen for a permanent bond.

  • Check Bond: Ensure the laminate is firmly glued down and not delaminating from the core substrate underneath.
  • Degloss: Thoroughly scuff-sand the entire surface using 80-grit sandpaper to create a rough, open texture.
  • Solvent Wipe: Wipe down completely with acetone or denatured alcohol to eliminate lingering dust, waxes, or silicone residue.
  • Prime: Apply 1 to 2 coats of MyPRIMER.

Universal Golden Rules for Substrate Preparation

  1. Rigidity is Essential (The Tap Test): Tap your substrate. If it sounds hollow, flexes underfoot, or crumbles under pressure, fix the structural flaw first. MyCROCEMENT™ is flexible, but it cannot structurally hold together a failing base under stress.
  2. Never Skip Primer: Priming neutralizes suction differences, prevents pinholing, extends troweling working time, and guarantees a chemical/mechanical bond to the substrate.
  3. Respect Movement & Expansion Joints: Never bridge active building expansion joints or concrete control joints with MyCROCEMENT™. Honor all structural expansion joints by carrying them up through the finished microcement layer or filling them with a color-matched flexible polyurethane sealant.
  4. Cleanliness Drives Adhesion: Dust, grease, and silicones are bond-killers. Always vacuum thoroughly using HEPA filtration right before priming.

Need Assistance?